D1: Critical path analysisEdexcel International A Level Maths: Topic test
20 questions, 54 marks
Edexcel International A Level Maths
D1: Critical path analysis topic test
Total 54 marks
Name
Class
Date
- 1A conference hall is prepared in five activities. Activities and have no predecessors. has immediate predecessor only. has immediate predecessors and . has immediate predecessors and . The project is modelled by an activity network, using activity on arc.(a)How many dummy activities are needed in the network?[1 mark]
- A
- B
- C
- D
(b)Where should the dummy be drawn?[1 mark]- AFrom the end of to the start of
- BFrom the end of to the start of
- CFrom the end of to the start of
- DFrom the end of to the start of
(c)Explain why a dummy activity is needed in the network.[2 marks]Total for question 1: 4 marks
- 2A house extension is modelled by an activity network with events numbered to . The activities, with the events they join and their durations in days, are (from event to , days), ( to , days), ( to , days), ( to , days), ( to , days) and ( to , days).(a)What is the minimum time in which the project can be completed?[1 mark]
- A days
- B days
- C days
- D days
(b)Which activities are critical?[1 mark]- A and
- B, and
- C, and
- D and
(c)Find the total float of activity .[2 marks]Total for question 2: 4 marks
- 3A stage set is built by an activity network with events numbered to . The activities, with the events they join and their durations in days, are ( to , ), ( to , ), ( to , ), ( to , ), ( to , ), ( to , ), ( to , ), ( to , ) and ( to , ). There is also a dummy activity from event to event .(a)Carry out a forward pass to find the earliest time of every event, and state the minimum completion time of the project.[3 marks](b)Carry out a backward pass, hence list the critical activities, and find the total float of activity .[4 marks]
Total for question 3: 7 marks
- 4A film crew prepares a set using nine activities. Their durations in hours and immediate predecessors are: (, none); (, none); (, none); (, ); (, and ); (, ); (, and ); (, ); (, and ). Each activity needs exactly one worker for its whole duration and cannot be split.(a)Find the minimum completion time of the project and the critical activities, and find the total float of activity .[6 marks](b)Show that at least workers are needed to complete the project in the minimum time, and construct a schedule that does it with workers.[6 marks]
Total for question 4: 12 marks
- 5A product launch is modelled by an activity network with events numbered to , using activity on arc. The activities, with the events they join, are ( to ), ( to ), ( to ), ( to ), ( to ), ( to ) and ( to ). There is a dummy activity from event to event .(a)What are the immediate predecessors of activity ?[1 mark]
- A and
- B only
- C only
- D and
(b)Activity is delayed. Which activities can still start as soon as is complete?[1 mark]- A, and
- B and
- C and
- D only
(c)Write down the immediate predecessors of activity and of activity .[2 marks]Total for question 5: 4 marks
- 6In an activity network, activity runs from event to event and has duration days. The earliest time of event is days and the latest time of event is days.(a)What is the total float of activity ?[1 mark]
- A days
- B days
- C days
- D days
(b)Activity takes days longer than planned. By how much is the project completion time delayed?[1 mark]- AIt is not delayed
- B days
- C days
- D days
(c)Explain why activity is not a critical activity.[2 marks]Total for question 6: 4 marks
- 7A kitchen refit has seven activities. Durations in hours and immediate predecessors are: (, none); (, none); (, ); (, ); (, and ); (, and ); (, ). Each activity needs exactly one worker for its whole duration and cannot be split.(a)Find the earliest start time of every activity and the minimum completion time of the project.[3 marks](b)Only two workers are available. Show that the project cannot be completed in hours, and construct a schedule that completes it in hours.[4 marks]
Total for question 7: 7 marks
- 8A railway repair is modelled by an activity network with events numbered to . The activities, with the events they join and their durations in days, are ( to , ), ( to , ), ( to , ), ( to , ), ( to , ), ( to , ) and ( to , ). There is a dummy activity from event to event .(a)Carry out a forward pass and a backward pass. Hence state the minimum completion time, the critical activities, and the total float of activity .[6 marks](b)Activity is found to take days instead of . Find the new minimum completion time and the new critical activities. Use the total float of to explain why the project is delayed by less than days.[6 marks]
Total for question 8: 12 marks
End of questions
Written by the Exaim team, led by Shaun Daswani (Head of Upper Secondary, Improve ME Institute; MSc Financial Mathematics, Imperial College London; BSc, UCL) and Jason Daswani (operational lead, Improve ME Institute; LSE).