All topic tests topics

D1: Critical path analysisEdexcel International A Level Maths: Topic test

20 questions, 54 marks

Edexcel International A Level Maths

D1: Critical path analysis topic test

Total 54 marks

Name

Class

Date

  1. 1
    A conference hall is prepared in five activities. Activities AA and BB have no predecessors. CC has immediate predecessor AA only. DD has immediate predecessors AA and BB. EE has immediate predecessors CC and DD. The project is modelled by an activity network, using activity on arc.
    (a)
    How many dummy activities are needed in the network?
    [1 mark]
    • A00
    • B11
    • C22
    • D33
    (b)
    Where should the dummy be drawn?
    [1 mark]
    • AFrom the end of BB to the start of CC
    • BFrom the end of CC to the start of EE
    • CFrom the end of AA to the start of DD
    • DFrom the end of DD to the start of EE
    (c)
    Explain why a dummy activity is needed in the network.
    [2 marks]

    Total for question 1: 4 marks

  2. 2
    A house extension is modelled by an activity network with events numbered 11 to 55. The activities, with the events they join and their durations in days, are AA (from event 11 to 22, 44 days), BB (11 to 33, 66 days), CC (22 to 44, 55 days), DD (33 to 44, 33 days), EE (33 to 55, 77 days) and FF (44 to 55, 22 days).
    (a)
    What is the minimum time in which the project can be completed?
    [1 mark]
    • A1111 days
    • B2727 days
    • C99 days
    • D1313 days
    (b)
    Which activities are critical?
    [1 mark]
    • ABB and EE
    • BAA, CC and FF
    • CBB, DD and FF
    • DEE and FF
    (c)
    Find the total float of activity CC.
    [2 marks]

    Total for question 2: 4 marks

  3. 3
    A stage set is built by an activity network with events numbered 11 to 77. The activities, with the events they join and their durations in days, are AA (11 to 22, 55), BB (11 to 33, 44), CC (22 to 44, 66), DD (22 to 55, 33), EE (33 to 55, 77), FF (33 to 66, 22), GG (44 to 77, 44), HH (55 to 77, 55) and II (66 to 77, 66). There is also a dummy activity from event 44 to event 55.
    (a)
    Carry out a forward pass to find the earliest time of every event, and state the minimum completion time of the project.
    [3 marks]
    (b)
    Carry out a backward pass, hence list the critical activities, and find the total float of activity GG.
    [4 marks]

    Total for question 3: 7 marks

  4. 4
    A film crew prepares a set using nine activities. Their durations in hours and immediate predecessors are: AA (55, none); BB (44, none); CC (33, none); DD (66, AA); EE (44, AA and BB); FF (55, CC); GG (33, DD and EE); HH (44, FF); II (22, GG and HH). Each activity needs exactly one worker for its whole duration and cannot be split.
    (a)
    Find the minimum completion time of the project and the critical activities, and find the total float of activity HH.
    [6 marks]
    (b)
    Show that at least 33 workers are needed to complete the project in the minimum time, and construct a schedule that does it with 33 workers.
    [6 marks]

    Total for question 4: 12 marks

  5. 5
    A product launch is modelled by an activity network with events numbered 11 to 66, using activity on arc. The activities, with the events they join, are AA (11 to 22), BB (11 to 33), CC (22 to 44), DD (33 to 44), EE (33 to 55), FF (44 to 66) and GG (55 to 66). There is a dummy activity from event 22 to event 33.
    (a)
    What are the immediate predecessors of activity EE?
    [1 mark]
    • AAA and BB
    • BAA only
    • CBB only
    • DCC and DD
    (b)
    Activity BB is delayed. Which activities can still start as soon as AA is complete?
    [1 mark]
    • ACC, DD and EE
    • BCC and DD
    • CDD and EE
    • DCC only
    (c)
    Write down the immediate predecessors of activity FF and of activity GG.
    [2 marks]

    Total for question 5: 4 marks

  6. 6
    In an activity network, activity XX runs from event 33 to event 55 and has duration 66 days. The earliest time of event 33 is 88 days and the latest time of event 55 is 2222 days.
    (a)
    What is the total float of activity XX?
    [1 mark]
    • A1414 days
    • B1616 days
    • C88 days
    • D3636 days
    (b)
    Activity XX takes 1010 days longer than planned. By how much is the project completion time delayed?
    [1 mark]
    • AIt is not delayed
    • B22 days
    • C1010 days
    • D88 days
    (c)
    Explain why activity XX is not a critical activity.
    [2 marks]

    Total for question 6: 4 marks

  7. 7
    A kitchen refit has seven activities. Durations in hours and immediate predecessors are: AA (44, none); BB (66, none); CC (33, AA); DD (55, AA); EE (44, BB and CC); FF (22, DD and EE); GG (33, DD). Each activity needs exactly one worker for its whole duration and cannot be split.
    (a)
    Find the earliest start time of every activity and the minimum completion time of the project.
    [3 marks]
    (b)
    Only two workers are available. Show that the project cannot be completed in 1313 hours, and construct a schedule that completes it in 1414 hours.
    [4 marks]

    Total for question 7: 7 marks

  8. 8
    A railway repair is modelled by an activity network with events numbered 11 to 66. The activities, with the events they join and their durations in days, are AA (11 to 22, 66), BB (11 to 33, 33), CC (22 to 44, 55), DD (33 to 44, 44), EE (33 to 55, 77), FF (44 to 66, 33) and GG (55 to 66, 22). There is a dummy activity from event 22 to event 33.
    (a)
    Carry out a forward pass and a backward pass. Hence state the minimum completion time, the critical activities, and the total float of activity CC.
    [6 marks]
    (b)
    Activity CC is found to take 88 days instead of 55. Find the new minimum completion time and the new critical activities. Use the total float of CC to explain why the project is delayed by less than 33 days.
    [6 marks]

    Total for question 8: 12 marks

End of questions

Written by the Exaim team, led by Shaun Daswani (Head of Upper Secondary, Improve ME Institute; MSc Financial Mathematics, Imperial College London; BSc, UCL) and Jason Daswani (operational lead, Improve ME Institute; LSE).