Power and Work Done

Power and Work Done Test

Spec 4.1.1.4 · AQA GCSE Physics: Subtopic test

Studying this course? Keep your progress in one place.

Two ways to do this test

Question by question

One question at a time. Each answer is marked the moment you hand it in, so you learn as you go. Drago helps if you get stuck. All 10 questions, or just 5.

Exam mode

The whole paper in one go, timed like the real exam. Nothing is marked until you hand it in, then you get every mark explained.

10 questions, 27 marks

AQA GCSE Physics

Power and Work Done

Total 27 marks

Name

Class

Date

  1. 1
    Two removal workers each carry an identical wardrobe of weight 800 N up a flight of stairs of height 4 m. Worker A takes 20 s to climb the stairs and Worker B takes 30 s.
    (a)
    Two removal workers each carry an identical wardrobe up a flight of stairs of the same height. Worker A takes 20 s and Worker B takes 30 s. Which statement about the two workers is correct?
    [1 mark]
    • AWorker A does more work than Worker B
    • BWorker A has a greater power output than Worker B
    • CWorker B has a greater power output than Worker A
    • DWorker A and Worker B transfer the same amount of energy at the same rate
    Show the mark scheme

    Mark scheme

    Answer: B
    (b)
    Which equation correctly links power, work done and time?
    [1 mark]
    • AP = W x t
    • BP = W + t
    • CP = t / W
    • DP = W / t
    Show the mark scheme

    Mark scheme

    Answer: D
    (c)
    Calculate the power output of Worker A while carrying the wardrobe up the stairs. Show the equation used, your working, and give the final answer with unit.
    [2 marks]
    Show the mark scheme

    Mark scheme

    [1] work done = force × distance: 800 × 4 = 3200 J, then P = W / t = 3200 / 20
    Accept: P = E / t

    [1] 160 W

    Do not accept: correct value with no unit

    Total for question 1: 4 marks

  2. 2
    A tug boat pulls a barge along a canal using a horizontal rope with a tension force of 12000 N. The barge moves 50 m along the line of the rope's pull, taking 100 s.
    (a)
    What quantity does the product of the force and the distance moved represent?
    [1 mark]
    • AThe power delivered by the tug boat
    • BThe momentum of the barge
    • CThe work done by the tug boat on the barge
    • DThe elastic potential energy of the rope
    Show the mark scheme

    Mark scheme

    Answer: C
    (b)
    Which unit is equivalent to one joule?
    [1 mark]
    • AOne newton-metre
    • BOne newton per metre
    • COne newton per second
    • DOne watt per second
    Show the mark scheme

    Mark scheme

    Answer: A
    (c)
    Calculate the power delivered by the tug boat's rope as it pulls the barge along the canal. Show the equation used, your working, and give the final answer with unit.
    [2 marks]
    Show the mark scheme

    Mark scheme

    [1] work done = force × distance: 12 000 × 50 = 600 000 J, then P = W / t = 600 000 / 100
    [1] 6000 W

    Accept: 6 kW

    Do not accept: correct value with no unit

    Total for question 2: 4 marks

  3. 3
    A hospital lift motor can raise a fully loaded lift car of weight 15000 N through a height of 12 m in 15 s. The hospital wants to install a faster motor to raise the same lift car through the same height in only 9 s.
    (a)
    Calculate the useful power output of the lift motor, giving your answer to an appropriate number of significant figures.
    [3 marks]
    Show the mark scheme

    Mark scheme

    [1] work done = force × distance: 15 000 × 12 = 180 000 J
    [1] correct substitution: P = W / t = 180 000 / 15

    [1] 12 000 W

    Accept: 12 kW; 1.2 × 10⁴ W

    Do not accept: correct value with no unit
    (b)
    The hospital wants to install a faster lift motor so that the same lift car can be raised through the same height of 12 m in only 9 s instead of 15 s. Explain what must be true about the new motor's power output compared with the original motor, and calculate the minimum power output required for the new motor.
    [4 marks]
    Show the mark scheme

    Mark scheme

    [1] the new motor must have a greater power output, because it does the same work in less time
    Accept: power is the rate of doing work

    [1] work done is unchanged: 15 000 × 12 = 180 000 J

    [1] correct substitution: P = W / t = 180 000 / 9

    [1] 20 000 W

    Accept: 20 kW

    Do not accept: correct value with no unit

    Total for question 3: 7 marks

  4. 4
    Two competing manufacturers advertise electric bicycle motors: Motor X (250 W) and Motor Y (400 W). A cyclist and bicycle of total mass 90 kg want to climb a hill that rises 20 m vertically, using one of these motors.
    (a)
    Explain what is meant by power in this context, and use the concept of power to explain and calculate how long each motor would take to lift the cyclist and bicycle up the hill, assuming all the motor's power is usefully transferred to gravitational potential energy store of the cyclist and no energy is transferred to the thermal energy store.
    [6 marks]
    Show the mark scheme

    Mark scheme

    [1] power is the rate at which energy is transferred (or work is done)
    Accept: energy transferred per second; joules per second

    [1] gravitational potential energy gained: mgh = 90 × 9.8 × 20 = 17 640 J

    Accept: g = 10 N/kg giving 18 000 J

    [1] rearrangement of P = E / t to t = E / P

    [1] Motor X: t = 17 640 / 250 = 70.6 s

    Accept: 70 to 71 s; 72 s if g = 10 N/kg is used

    [1] Motor Y: t = 17 640 / 400 = 44.1 s

    Accept: 44 s; 45 s if g = 10 N/kg is used

    [1] Motor Y has the higher power, so it transfers the same energy in less time and gets the cyclist up the hill faster
    (b)
    In reality, not all of the electrical energy supplied to an electric bicycle motor is transferred usefully to the gravitational potential energy store of the cyclist when climbing a hill. Evaluate the factors that would cause the actual time taken to climb the hill to be longer than the calculated times for Motor X and Motor Y, and discuss how a manufacturer could design a motor system to reduce these losses.
    [6 marks]
    Show the mark scheme

    Mark scheme

    [1] some energy is transferred to the thermal energy store of the motor because of resistance heating in the windings
    [1] some energy is transferred to the thermal energy store by friction in the chain, gears and bearings

    [1] some energy is transferred to the kinetic energy store of the air by air resistance

    Accept: wasted as sound

    [1] less useful energy reaches the gravitational potential energy store each second, so the climb takes longer than calculated

    [1] reduction method 1: more efficient motor or lower resistance windings, reducing heating losses

    [1] reduction method 2: lubricate the chain, gears and bearings, or use better bearings, reducing friction

    Accept: streamlined shape or lower profile to reduce air resistance

    Total for question 4: 12 marks