Activity networks and precedence tables

Activity networks and precedence tables Quiz

Spec 4.1–2 · Edexcel International A Level Maths: Quiz

Studying this course? Keep your progress in one place.

Pick an answer for each. Quizzes never use energy.

5 questions, one answer each

Each answer is checked as you go, with why.

See all 5 questions
  1. 1. In an activity-on-arc network, what does an arc represent?

    • A. An event
    • B. An activity
    • C. A float
    • D. A critical path
  2. 2. What is the duration of a dummy activity?

    • A. One unit
    • B. The shortest activity duration
    • C. Zero
    • D. The same as the previous activity
  3. 3. Activities X and Y both have W as their only immediate predecessor, and Z follows both. Without a dummy, why is the network ambiguous?

    • A. Z would start too early
    • B. W would have two durations
    • C. Both X and Y would run between the same two events
    • D. The network would have two start events
  4. 4. K has immediate predecessors G and H; L has immediate predecessor G only. G and H have no other successors. Which drawing shows this?

    • A. L starts at the end of G; K starts at the end of H, with a dummy from the end of G to the start of K
    • B. K and L both start at the end of G
    • C. L starts at the end of H; K starts at the end of G
    • D. A dummy from the end of K to the start of L
  5. 5. A must precede C, and C must precede F. Nothing else precedes F. What is listed against F in the precedence table?

    • A. A and C
    • B. C only
    • C. A only
    • D. No predecessors

Quiz