Critical paths and float Quiz
Studying this course? Keep your progress in one place.
Pick an answer for each. Quizzes never use energy.
5 questions, one answer each
Each answer is checked as you go, with why.
See all 5 questions
1. In a forward pass, two activities arrive at an event. How is its earliest event time found?
- A. The smaller of the two arrival times
- B. The mean of the two arrival times
- C. The larger of the two arrival times
- D. The sum of the two arrival times
2. In a backward pass, two activities leave an event. How is its latest event time found?
- A. The smaller of the two values
- B. The larger of the two values
- C. The mean of the two values
- D. The earliest event time
3. Which is the correct formula for the total float of an activity from event to event with duration ?
- A.
- B.
- C.
- D.
4. An activity has a total float of 0. Which statement must be true?
- A. It is the shortest activity
- B. Any delay to it delays the whole project
- C. It can start at any time
- D. It has no predecessors
5. An activity from event 2 to event 5 lasts 6 days. and . What is its total float?
- A. 3 days
- B. 2 days
- C. 7 days
- D. 9 days