Activity networks and precedence tablesEdexcel International A Level Maths: Subtopic test
10 questions, 27 marks
Edexcel International A Level Maths
Activity networks and precedence tables
Total 27 marks
Name
Class
Date
- 1A project has five activities, A to E. Activities A and B have no predecessors. C has immediate predecessor A only. D has immediate predecessors A and B. E has immediate predecessors C and D. The project is modelled by an activity network with activities on arcs.(a)Which activity can start as soon as A has finished, even if B has not yet finished?[1 mark]
- AC and D
- BD only
- CC only
- DE only
(b)A student draws D starting at the event where B finishes, with no dummy, and C starting at the event where A finishes. What is wrong with this network?[1 mark]- AD would not depend on A
- BC would depend on B as well as A
- CE would not depend on C
- DB would depend on A
(c)Explain why the correct network needs a dummy activity, and state where the dummy is drawn.[2 marks]Total for question 1: 4 marks
- 2A project has six activities, P to U. P and Q have no predecessors. R has immediate predecessor P only. S has immediate predecessors P and Q. T has immediate predecessor Q only. U has immediate predecessors R, S and T. The project is modelled by an activity-on-arc network.(a)Which activities have more than one immediate predecessor?[1 mark]
- AS only
- BR and T
- CS, T and U
- DS and U
(b)What is the minimum number of dummy activities needed in an activity-on-arc network for this project?[1 mark]- A1
- B2
- C3
- D4
(c)Explain why S needs dummy activities but R and T do not.[2 marks]Total for question 2: 4 marks
- 3An activity network has start event 1 and finish event 6. Its arcs are: A from event 1 to event 2; B from 1 to 3; C from 2 to 4; a dummy from 2 to 3; D from 3 to 4; E from 3 to 5; F from 4 to 6; G from 5 to 6.(a)Write down the immediate predecessors of each of the activities A, B, C, D, E, F and G.[3 marks](b)A new activity H is added, with immediate predecessors C and E only. F and G keep their predecessors. Explain why H cannot simply start at event 4, and describe how the network must be redrawn.[4 marks]
Total for question 3: 7 marks
- 4A project has activities A to G. A, B and C have no predecessors. D has immediate predecessor A only. E has immediate predecessors A and B. F has immediate predecessors B and C. G has immediate predecessors D, E and F, and is the last activity. The project is modelled by an activity-on-arc network with a single start event, event 1.(a)Describe a valid network for this project using exactly 3 dummy activities, by stating the start event and finish event of every activity and dummy.[6 marks](b)A further activity H is added, with immediate predecessors D and F only. H is also a last activity, and G must still follow D, E and F. Describe the changes needed to your network from (a) and state how many dummy activities it now has.[6 marks]
Total for question 4: 12 marks
End of questions
Written by the Exaim team, led by Shaun Daswani (Head of Upper Secondary, Improve ME Institute; MSc Financial Mathematics, Imperial College London; BSc, UCL) and Jason Daswani (operational lead, Improve ME Institute; LSE).