All worksheets topics

Activity networks and precedence tablesEdexcel International A Level Maths: Subtopic test

10 questions, 27 marks

Edexcel International A Level Maths

Activity networks and precedence tables

Total 27 marks

Name

Class

Date

  1. 1
    A project has five activities, A to E. Activities A and B have no predecessors. C has immediate predecessor A only. D has immediate predecessors A and B. E has immediate predecessors C and D. The project is modelled by an activity network with activities on arcs.
    (a)
    Which activity can start as soon as A has finished, even if B has not yet finished?
    [1 mark]
    • AC and D
    • BD only
    • CC only
    • DE only
    (b)
    A student draws D starting at the event where B finishes, with no dummy, and C starting at the event where A finishes. What is wrong with this network?
    [1 mark]
    • AD would not depend on A
    • BC would depend on B as well as A
    • CE would not depend on C
    • DB would depend on A
    (c)
    Explain why the correct network needs a dummy activity, and state where the dummy is drawn.
    [2 marks]

    Total for question 1: 4 marks

  2. 2
    A project has six activities, P to U. P and Q have no predecessors. R has immediate predecessor P only. S has immediate predecessors P and Q. T has immediate predecessor Q only. U has immediate predecessors R, S and T. The project is modelled by an activity-on-arc network.
    (a)
    Which activities have more than one immediate predecessor?
    [1 mark]
    • AS only
    • BR and T
    • CS, T and U
    • DS and U
    (b)
    What is the minimum number of dummy activities needed in an activity-on-arc network for this project?
    [1 mark]
    • A1
    • B2
    • C3
    • D4
    (c)
    Explain why S needs dummy activities but R and T do not.
    [2 marks]

    Total for question 2: 4 marks

  3. 3
    An activity network has start event 1 and finish event 6. Its arcs are: A from event 1 to event 2; B from 1 to 3; C from 2 to 4; a dummy from 2 to 3; D from 3 to 4; E from 3 to 5; F from 4 to 6; G from 5 to 6.
    (a)
    Write down the immediate predecessors of each of the activities A, B, C, D, E, F and G.
    [3 marks]
    (b)
    A new activity H is added, with immediate predecessors C and E only. F and G keep their predecessors. Explain why H cannot simply start at event 4, and describe how the network must be redrawn.
    [4 marks]

    Total for question 3: 7 marks

  4. 4
    A project has activities A to G. A, B and C have no predecessors. D has immediate predecessor A only. E has immediate predecessors A and B. F has immediate predecessors B and C. G has immediate predecessors D, E and F, and is the last activity. The project is modelled by an activity-on-arc network with a single start event, event 1.
    (a)
    Describe a valid network for this project using exactly 3 dummy activities, by stating the start event and finish event of every activity and dummy.
    [6 marks]
    (b)
    A further activity H is added, with immediate predecessors D and F only. H is also a last activity, and G must still follow D, E and F. Describe the changes needed to your network from (a) and state how many dummy activities it now has.
    [6 marks]

    Total for question 4: 12 marks

End of questions

Written by the Exaim team, led by Shaun Daswani (Head of Upper Secondary, Improve ME Institute; MSc Financial Mathematics, Imperial College London; BSc, UCL) and Jason Daswani (operational lead, Improve ME Institute; LSE).