All flashcards topics

Critical paths and floatEdexcel International A Level Maths: Flashcards

Card 1 of 140 of 14 known

Question

How do you find an earliest event time?

Tap or press Space to reveal

Tap card or press Space to flip

See all 14 cards
How do you find an earliest event time?
Forward pass: take the largest of e(i)+de(i)+d over all activities arriving at the event; e(1)=0e(1)=0.
How do you find a latest event time?
Backward pass: take the smallest of l(j)−dl(j)-d over all activities leaving the event; l(n)=e(n)l(n)=e(n).
What is the minimum project duration?
The earliest event time at the finish event.
What is l(1)l(1) in a correct backward pass?
00 (a useful check on your arithmetic).
Earliest start time of an activity from event ii to jj?
e(i)e(i)
Earliest finish time of an activity from event ii to jj with duration dd?
e(i)+de(i)+d
Latest finish time of an activity from event ii to jj?
l(j)l(j)
Latest start time of an activity from event ii to jj with duration dd?
l(j)−dl(j)-d
State the total float formula.
F(i,j)=l(j)−e(i)−d(i,j)F(i,j)=l(j)-e(i)-d(i,j)
What does a total float of 0 mean?
The activity is critical: any delay delays the whole project.
What is the critical path?
A path of critical activities from start to finish; its length is the minimum project duration.
Can a network have more than one critical path?
Yes: if two or more routes have the same longest length.
Why can a forward pass use a dummy of duration 0?
The dummy still forces its end event to wait: e(j)≥e(i)+0e(j)\ge e(i)+0.
What does float of 4 days on an activity mean?
It can be delayed by up to 4 days (starting at its earliest time) without delaying the project.

Exam questions on Critical paths and float

  1. A project is modelled by an activity network with start event 1 and finish event 6. The activities are: A from event 1 to 2 (3 days); B from 1 to 3 (5 days); C from 2 to 4 (6 days); D from 3 to 4 (2 days); E from 3 to 5 (4 days); F from 4 to 6 (3 days); G from 5 to 6 (5 days).
    Calculate the total float on activity D.2 marks
  2. A project is modelled by an activity network with start event 1 and finish event 5. The activities are: A from event 1 to 2 (6 days); B from 1 to 3 (4 days); C from 2 to 4 (3 days); a dummy from 2 to 3; D from 3 to 4 (7 days); E from 4 to 5 (5 days); F from 3 to 5 (9 days).
    Find the earliest finish time and the latest finish time of activity B, and hence its total float.2 marks
  3. A project is modelled by an activity network with start event 1 and finish event 5. The activities are: A from event 1 to 2 (5 days); B from 1 to 3 (7 days); C from 2 to 4 (6 days); D from 3 to 4 (5 days); E from 3 to 5 (8 days); F from 4 to 5 (3 days).
    Carry out a forward pass and state the minimum project duration.3 marks
See the full worksheet

Written by the Exaim team, led by Shaun Daswani (Head of Upper Secondary, Improve ME Institute; MSc Financial Mathematics, Imperial College London; BSc, UCL) and Jason Daswani (operational lead, Improve ME Institute; LSE).