Critical paths and float Flashcards
Studying this course? Keep your progress in one place.

Flip each card. Be honest: the ones you mark Not yet come back first.
14 cards
Tap a card to flip it. Swipe right if you knew it, left if not.
See all 14 cards
- How do you find an earliest event time?
- Forward pass: take the largest of over all activities arriving at the event; .
- How do you find a latest event time?
- Backward pass: take the smallest of over all activities leaving the event; .
- What is the minimum project duration?
- The earliest event time at the finish event.
- What is in a correct backward pass?
- (a useful check on your arithmetic).
- Earliest start time of an activity from event to ?
- Earliest finish time of an activity from event to with duration ?
- Latest finish time of an activity from event to ?
- Latest start time of an activity from event to with duration ?
- State the total float formula.
- What does a total float of 0 mean?
- The activity is critical: any delay delays the whole project.
- What is the critical path?
- A path of critical activities from start to finish; its length is the minimum project duration.
- Can a network have more than one critical path?
- Yes: if two or more routes have the same longest length.
- Why can a forward pass use a dummy of duration 0?
- The dummy still forces its end event to wait: .
- What does float of 4 days on an activity mean?
- It can be delayed by up to 4 days (starting at its earliest time) without delaying the project.