Critical paths and floatEdexcel International A Level Maths: Flashcards
Card 1 of 140 of 14 known
Question
How do you find an earliest event time?
Tap or press Space to reveal
Tap card or press Space to flip
See all 14 cards
- How do you find an earliest event time?
- Forward pass: take the largest of over all activities arriving at the event; .
- How do you find a latest event time?
- Backward pass: take the smallest of over all activities leaving the event; .
- What is the minimum project duration?
- The earliest event time at the finish event.
- What is in a correct backward pass?
- (a useful check on your arithmetic).
- Earliest start time of an activity from event to ?
- Earliest finish time of an activity from event to with duration ?
- Latest finish time of an activity from event to ?
- Latest start time of an activity from event to with duration ?
- State the total float formula.
- What does a total float of 0 mean?
- The activity is critical: any delay delays the whole project.
- What is the critical path?
- A path of critical activities from start to finish; its length is the minimum project duration.
- Can a network have more than one critical path?
- Yes: if two or more routes have the same longest length.
- Why can a forward pass use a dummy of duration 0?
- The dummy still forces its end event to wait: .
- What does float of 4 days on an activity mean?
- It can be delayed by up to 4 days (starting at its earliest time) without delaying the project.
Exam questions on Critical paths and float
- A project is modelled by an activity network with start event 1 and finish event 6. The activities are: A from event 1 to 2 (3 days); B from 1 to 3 (5 days); C from 2 to 4 (6 days); D from 3 to 4 (2 days); E from 3 to 5 (4 days); F from 4 to 6 (3 days); G from 5 to 6 (5 days).Calculate the total float on activity D.2 marks
- A project is modelled by an activity network with start event 1 and finish event 5. The activities are: A from event 1 to 2 (6 days); B from 1 to 3 (4 days); C from 2 to 4 (3 days); a dummy from 2 to 3; D from 3 to 4 (7 days); E from 4 to 5 (5 days); F from 3 to 5 (9 days).Find the earliest finish time and the latest finish time of activity B, and hence its total float.2 marks
- A project is modelled by an activity network with start event 1 and finish event 5. The activities are: A from event 1 to 2 (5 days); B from 1 to 3 (7 days); C from 2 to 4 (6 days); D from 3 to 4 (5 days); E from 3 to 5 (8 days); F from 4 to 5 (3 days).Carry out a forward pass and state the minimum project duration.3 marks
Written by the Exaim team, led by Shaun Daswani (Head of Upper Secondary, Improve ME Institute; MSc Financial Mathematics, Imperial College London; BSc, UCL) and Jason Daswani (operational lead, Improve ME Institute; LSE).