All worksheets topics

Critical paths and floatEdexcel International A Level Maths: Subtopic test

10 questions, 27 marks

Edexcel International A Level Maths

Critical paths and float

Total 27 marks

Name

Class

Date

  1. 1
    A project is modelled by an activity network with start event 1 and finish event 6. The activities are: A from event 1 to 2 (3 days); B from 1 to 3 (5 days); C from 2 to 4 (6 days); D from 3 to 4 (2 days); E from 3 to 5 (4 days); F from 4 to 6 (3 days); G from 5 to 6 (5 days).
    (a)
    Carry out a forward pass. What is the earliest event time at event 4?
    [1 mark]
    • A7 days
    • B11 days
    • C14 days
    • D9 days
    (b)
    The minimum project duration is 14 days. Carry out a backward pass. What is the latest event time at event 2?
    [1 mark]
    • A5 days
    • B3 days
    • C8 days
    • D9 days
    (c)
    Calculate the total float on activity D.
    [2 marks]

    Total for question 1: 4 marks

  2. 2
    A project is modelled by an activity network with start event 1 and finish event 5. The activities are: A from event 1 to 2 (6 days); B from 1 to 3 (4 days); C from 2 to 4 (3 days); a dummy from 2 to 3; D from 3 to 4 (7 days); E from 4 to 5 (5 days); F from 3 to 5 (9 days).
    (a)
    Which of these is the critical path?
    [1 mark]
    • AA, C, E
    • BA, dummy, D, E
    • CB, D, E
    • DA, dummy, F
    (b)
    What is the latest start time of activity C, relative to the start of the project?
    [1 mark]
    • A6 days
    • B9 days
    • C10 days
    • D13 days
    (c)
    Find the earliest finish time and the latest finish time of activity B, and hence its total float.
    [2 marks]

    Total for question 2: 4 marks

  3. 3
    A project is modelled by an activity network with start event 1 and finish event 5. The activities are: A from event 1 to 2 (5 days); B from 1 to 3 (7 days); C from 2 to 4 (6 days); D from 3 to 4 (5 days); E from 3 to 5 (8 days); F from 4 to 5 (3 days).
    (a)
    Carry out a forward pass and state the minimum project duration.
    [3 marks]
    (b)
    Carry out a backward pass, and hence find all the critical paths.
    [4 marks]

    Total for question 3: 7 marks

  4. 4
    A project is modelled by an activity network with start event 1 and finish event 6. The activities are: A from event 1 to 2 (4 days); B from 1 to 3 (6 days); C from 2 to 4 (7 days); D from 3 to 4 (3 days); E from 2 to 5 (6 days); F from 3 to 5 (5 days); G from 4 to 6 (6 days); H from 5 to 6 (4 days).
    (a)
    Find the minimum project duration, the critical path, and the total float on activity E.
    [6 marks]
    (b)
    Extra staff can reduce the duration of C by up to 3 days. Find the minimum project duration if C is reduced by 3 days, and explain why the project duration is not reduced by 3 days.
    [6 marks]

    Total for question 4: 12 marks

End of questions

Written by the Exaim team, led by Shaun Daswani (Head of Upper Secondary, Improve ME Institute; MSc Financial Mathematics, Imperial College London; BSc, UCL) and Jason Daswani (operational lead, Improve ME Institute; LSE).