Activity networks and critical paths Quiz
Studying this course? Keep your progress in one place.
Pick an answer for each. Quizzes never use energy.
5 questions, one answer each
Each answer is checked as you go, with why.
See all 5 questions
1. In an activity-on-node network there are arrows from and from into . What does this mean?
- A. must finish before and
- B. and must both finish before can start
- C. can start when either or finishes
- D. , and all start together
2. An activity has predecessors with earliest finish times 8 and 11. What is its earliest start time?
- A. Day 11
- B. Day 8
- C. Day 19
- D. Day 3
3. An activity is followed by two activities whose latest start times are 14 and 10. What is its latest finish time?
- A. Day 24
- B. Day 14
- C. Day 10
- D. Day 4
4. An activity has earliest start time 5, duration 4 and latest finish time 14. What is its float?
- A. 9 days
- B. 0 days
- C. 4 days
- D. 5 days
5. Which statement about a critical activity is true?
- A. It has the longest duration
- B. Any delay to it delays the project
- C. It has positive float
- D. It has no predecessors