Activity networks and critical paths

Activity networks and critical paths Quiz

Spec DE1–DE4 · AQA A-Level Further Maths: Quiz

Studying this course? Keep your progress in one place.

Pick an answer for each. Quizzes never use energy.

5 questions, one answer each

Each answer is checked as you go, with why.

See all 5 questions
  1. 1. In an activity-on-node network there are arrows from BB and from CC into EE. What does this mean?

    • A. EE must finish before BB and CC
    • B. BB and CC must both finish before EE can start
    • C. EE can start when either BB or CC finishes
    • D. BB, CC and EE all start together
  2. 2. An activity has predecessors with earliest finish times 8 and 11. What is its earliest start time?

    • A. Day 11
    • B. Day 8
    • C. Day 19
    • D. Day 3
  3. 3. An activity is followed by two activities whose latest start times are 14 and 10. What is its latest finish time?

    • A. Day 24
    • B. Day 14
    • C. Day 10
    • D. Day 4
  4. 4. An activity has earliest start time 5, duration 4 and latest finish time 14. What is its float?

    • A. 9 days
    • B. 0 days
    • C. 4 days
    • D. 5 days
  5. 5. Which statement about a critical activity is true?

    • A. It has the longest duration
    • B. Any delay to it delays the project
    • C. It has positive float
    • D. It has no predecessors

Quiz