Activity networks and critical pathsAQA A-Level Further Maths: Flashcards
Card 1 of 130 of 13 known
Question
What is an activity-on-node network?
Tap or press Space to reveal
Tap card or press Space to flip
See all 13 cards
- What is an activity-on-node network?
- A network in which each activity is a node, and arrows show which activities must be finished first.
- What are immediate predecessors?
- The activities that must finish before an activity can start, with none in between.
- How is the earliest start time of an activity found?
- The maximum of the earliest finish times of its immediate predecessors (0 if it has none).
- How is the earliest finish time found?
- Earliest start time plus duration.
- What is the minimum completion time?
- The largest earliest finish time, the length of the longest path.
- How is the latest finish time of an activity found?
- The minimum of the latest start times of its immediate successors.
- How is the latest start time found?
- Latest finish time minus duration.
- How do you calculate float?
- Latest finish minus earliest start minus duration (or latest start minus earliest start).
- What is a critical activity?
- An activity with zero float; delaying it delays the whole project.
- What is a critical path?
- A path of critical activities from start to end whose length equals the minimum completion time.
- Can a project have more than one critical path?
- Yes.
- What happens if a non-critical activity is delayed by more than its float?
- The project is delayed by the excess over the float.
- When does shortening an activity reduce the project time?
- Only if it lies on every critical path, and only until another path becomes critical.
Exam questions on Activity networks and critical paths
- A project has seven activities, to , shown in an activity-on-node network. The durations in days and the immediate predecessors are: 3 (none), 5 (none), 4 (), 6 ( and ), 2 (), 4 ( and ) and 3 ( and ).Find the float on activity and explain what it means.2 marks
- A different project has seven activities, to . The durations in days and the immediate predecessors are: 4 (none), 6 (none), 5 (), 3 (), 4 ( and ), 7 () and 2 ( and ). The project has a minimum completion time of 16 days.Activity is delayed by 2 days. State the effect on the completion time of the project, with working.2 marks
- A project has seven activities, to , in an activity-on-node network. The durations in days and the immediate predecessors are: 5 (none), 3 (none), 4 (), 6 (), 2 ( and ), 5 ( and ) and 4 ( and ).Find the earliest start times of activities , and .3 marks
Written by the Exaim team, led by Shaun Daswani (Head of Upper Secondary, Improve ME Institute; MSc Financial Mathematics, Imperial College London; BSc, UCL) and Jason Daswani (operational lead, Improve ME Institute; LSE).