Activity networks and critical pathsAQA A-Level Further Maths: Mind map

Activity network
Forward pass

Critical path analysis

activity-on-node

forward passbackward passfloat
Backward pass
Float and critical
Refining

Exam questions on Activity networks and critical paths

  1. A project has seven activities, AA to GG, shown in an activity-on-node network. The durations in days and the immediate predecessors are: AA 3 (none), BB 5 (none), CC 4 (AA), DD 6 (AA and BB), EE 2 (CC), FF 4 (CC and DD) and GG 3 (EE and FF).
    Find the float on activity CC and explain what it means.2 marks
  2. A different project has seven activities, AA to GG. The durations in days and the immediate predecessors are: AA 4 (none), BB 6 (none), CC 5 (AA), DD 3 (AA), EE 4 (BB and CC), FF 7 (DD) and GG 2 (EE and FF). The project has a minimum completion time of 16 days.
    Activity CC is delayed by 2 days. State the effect on the completion time of the project, with working.2 marks
  3. A project has seven activities, AA to GG, in an activity-on-node network. The durations in days and the immediate predecessors are: AA 5 (none), BB 3 (none), CC 4 (AA), DD 6 (AA), EE 2 (BB and CC), FF 5 (BB and DD) and GG 4 (EE and FF).
    Find the earliest start times of activities EE, FF and GG.3 marks