Activity networks and critical pathsAQA A-Level Further Maths: Mind map
Activity network
Forward pass
Critical path analysis
activity-on-node
forward passbackward passfloat
Backward pass
Float and critical
Refining
Exam questions on Activity networks and critical paths
- A project has seven activities, to , shown in an activity-on-node network. The durations in days and the immediate predecessors are: 3 (none), 5 (none), 4 (), 6 ( and ), 2 (), 4 ( and ) and 3 ( and ).Find the float on activity and explain what it means.2 marks
- A different project has seven activities, to . The durations in days and the immediate predecessors are: 4 (none), 6 (none), 5 (), 3 (), 4 ( and ), 7 () and 2 ( and ). The project has a minimum completion time of 16 days.Activity is delayed by 2 days. State the effect on the completion time of the project, with working.2 marks
- A project has seven activities, to , in an activity-on-node network. The durations in days and the immediate predecessors are: 5 (none), 3 (none), 4 (), 6 (), 2 ( and ), 5 ( and ) and 4 ( and ).Find the earliest start times of activities , and .3 marks