Activity networks and critical pathsAQA A-Level Further Maths: Subtopic test
10 questions, 27 marks
AQA A-Level Further Maths
Activity networks and critical paths
Total 27 marks
Name
Class
Date
- 1A project has seven activities, to , shown in an activity-on-node network. The durations in days and the immediate predecessors are: 3 (none), 5 (none), 4 (), 6 ( and ), 2 (), 4 ( and ) and 3 ( and ).(a)What is the earliest start time of activity ?[1 mark]
- ADay 11
- BDay 7
- CDay 15
- DDay 4
(b)What is the minimum completion time of the project?[1 mark]- A14 days
- B15 days
- C16 days
- D18 days
(c)Find the float on activity and explain what it means.[2 marks]Total for question 1: 4 marks
- 2A different project has seven activities, to . The durations in days and the immediate predecessors are: 4 (none), 6 (none), 5 (), 3 (), 4 ( and ), 7 () and 2 ( and ). The project has a minimum completion time of 16 days.(a)What is the latest finish time of activity for the project to finish in 16 days?[1 mark]
- ADay 16
- BDay 14
- CDay 13
- DDay 10
(b)Which activities are not critical?[1 mark]- A, , and
- B and only
- C, and
- D and only
(c)Activity is delayed by 2 days. State the effect on the completion time of the project, with working.[2 marks]Total for question 2: 4 marks
- 3A project has seven activities, to , in an activity-on-node network. The durations in days and the immediate predecessors are: 5 (none), 3 (none), 4 (), 6 (), 2 ( and ), 5 ( and ) and 4 ( and ).(a)Find the earliest start times of activities , and .[3 marks](b)Find the minimum completion time, the critical path and the float on activity .[4 marks]
Total for question 3: 7 marks
- 4A building project has eight activities. The durations in days and the immediate predecessors are: 6 (none), 4 (none), 5 (), 7 (), 3 (), 6 ( and ), 4 () and 5 ( and ).(a)Carry out a forward pass and a backward pass. State the minimum completion time, the critical activities, and the float on and on .[6 marks](b)The client wants the project to finish sooner. Activity could be shortened by up to 3 days at extra cost. Evaluate this, and suggest a better way to save one day.[6 marks]
Total for question 4: 12 marks
End of questions
Written by the Exaim team, led by Shaun Daswani (Head of Upper Secondary, Improve ME Institute; MSc Financial Mathematics, Imperial College London; BSc, UCL) and Jason Daswani (operational lead, Improve ME Institute; LSE).