All worksheets topics

Activity networks and critical pathsAQA A-Level Further Maths: Subtopic test

10 questions, 27 marks

AQA A-Level Further Maths

Activity networks and critical paths

Total 27 marks

Name

Class

Date

  1. 1
    A project has seven activities, AA to GG, shown in an activity-on-node network. The durations in days and the immediate predecessors are: AA 3 (none), BB 5 (none), CC 4 (AA), DD 6 (AA and BB), EE 2 (CC), FF 4 (CC and DD) and GG 3 (EE and FF).
    (a)
    What is the earliest start time of activity FF?
    [1 mark]
    • ADay 11
    • BDay 7
    • CDay 15
    • DDay 4
    (b)
    What is the minimum completion time of the project?
    [1 mark]
    • A14 days
    • B15 days
    • C16 days
    • D18 days
    (c)
    Find the float on activity CC and explain what it means.
    [2 marks]

    Total for question 1: 4 marks

  2. 2
    A different project has seven activities, AA to GG. The durations in days and the immediate predecessors are: AA 4 (none), BB 6 (none), CC 5 (AA), DD 3 (AA), EE 4 (BB and CC), FF 7 (DD) and GG 2 (EE and FF). The project has a minimum completion time of 16 days.
    (a)
    What is the latest finish time of activity EE for the project to finish in 16 days?
    [1 mark]
    • ADay 16
    • BDay 14
    • CDay 13
    • DDay 10
    (b)
    Which activities are not critical?
    [1 mark]
    • AAA, DD, FF and GG
    • BBB and CC only
    • CBB, CC and EE
    • DCC and EE only
    (c)
    Activity CC is delayed by 2 days. State the effect on the completion time of the project, with working.
    [2 marks]

    Total for question 2: 4 marks

  3. 3
    A project has seven activities, AA to GG, in an activity-on-node network. The durations in days and the immediate predecessors are: AA 5 (none), BB 3 (none), CC 4 (AA), DD 6 (AA), EE 2 (BB and CC), FF 5 (BB and DD) and GG 4 (EE and FF).
    (a)
    Find the earliest start times of activities EE, FF and GG.
    [3 marks]
    (b)
    Find the minimum completion time, the critical path and the float on activity CC.
    [4 marks]

    Total for question 3: 7 marks

  4. 4
    A building project has eight activities. The durations in days and the immediate predecessors are: AA 6 (none), BB 4 (none), CC 5 (AA), DD 7 (AA), EE 3 (BB), FF 6 (CC and EE), GG 4 (DD) and HH 5 (FF and GG).
    (a)
    Carry out a forward pass and a backward pass. State the minimum completion time, the critical activities, and the float on BB and on EE.
    [6 marks]
    (b)
    The client wants the project to finish sooner. Activity DD could be shortened by up to 3 days at extra cost. Evaluate this, and suggest a better way to save one day.
    [6 marks]

    Total for question 4: 12 marks

End of questions

Written by the Exaim team, led by Shaun Daswani (Head of Upper Secondary, Improve ME Institute; MSc Financial Mathematics, Imperial College London; BSc, UCL) and Jason Daswani (operational lead, Improve ME Institute; LSE).