Activity networks and precedence tables Quiz
Studying this course? Keep your progress in one place.
Pick an answer for each. Quizzes never use energy.
5 questions, one answer each
Each answer is checked as you go, with why.
See all 5 questions
1. In an activity-on-arc network, what does an arc represent?
- A. A start or finish time
- B. A dependency only
- C. A resource
- D. An activity
2. Why is a dummy activity used?
- A. To show a dependency without adding work or time
- B. To add extra time to the project
- C. To represent a worker
- D. To mark the end of the project
3. A and B have no predecessors. C needs A only and D needs A and B. How many dummy activities are needed?
- A. 0
- B. 2
- C. 1
- D. 3
4. C depends on A, and E depends on C. Which is the correct immediate predecessor entry for E?
- A. A and C
- B. C
- C. A
- D. The start
5. What is the duration of a dummy activity?
- A. 1
- B. The same as the previous activity
- C. Its own float
- D. 0