Critical paths and float Quiz
Studying this course? Keep your progress in one place.
Pick an answer for each. Quizzes never use energy.
5 questions, one answer each
Each answer is checked as you go, with why.
See all 5 questions
1. Two activities end at event k. One starts from an event with earliest time 6 and lasts 5 days; the other starts from an event with earliest time 8 and lasts 2 days. What is the earliest time at k?
- A. 10
- B. 11
- C. 13
- D. 16
2. In a backward pass, how is the latest event time at an event found?
- A. The largest of l(j) minus duration
- B. The average of the values
- C. The earliest event time
- D. The smallest of l(j) minus duration
3. An activity has e(i) = 4, l(j) = 11 and duration 5. What is its total float?
- A. 2
- B. 7
- C. 6
- D. 1
4. The durations total 45 days and the minimum project time is 20 days. What is the lower bound for the number of workers?
- A. 2
- B. 2.25
- C. 3
- D. 4
5. An activity has a total float of zero. What is it called?
- A. A dummy
- B. Critical
- C. A successor
- D. Spare