Activity networks and precedence tables

Activity networks and precedence tables Flashcards

Spec 4.1–2 · Edexcel A-Level Further Maths: Flashcards

Studying this course? Keep your progress in one place.

Flip each card. Be honest: the ones you mark Not yet come back first.

12 cards

Tap a card to flip it. Swipe right if you knew it, left if not.

See all 12 cards
What does an arc represent in an activity-on-arc network?
An activity.
What does a node represent?
An event, the start or finish of activities.
What is an immediate predecessor?
An activity that must be finished immediately before another can start.
What does a precedence table show?
Each activity with its immediate predecessors only.
If C depends on B and B depends on A, what does C's row show?
Only B.
What is a dummy activity?
A zero-duration arc that shows a dependency but has no work or resources.
When is a dummy needed for logic?
When two activities share some, but not all, of their predecessors.
Second use of a dummy?
To give two activities with the same start and end events different end events.
How are dummies drawn?
As dotted arrows.
How do you find an activity's predecessors from a network?
Look at the activities ending at its start event, including those reached through dummies.
Are dummies listed in a precedence table?
No; trace back through them to the real activities.
How many start events does the network have?
One.

Flashcards