All topic tests topics

Decision Mathematics 1: Critical path analysisEdexcel A-Level Further Maths: Topic test

20 questions, 54 marks

Edexcel A-Level Further Maths

Decision Mathematics 1: Critical path analysis topic test

Total 54 marks

Name

Class

Date

  1. 1
    A project is modelled by an activity network drawn with activities on arcs. The events are numbered 1 to 6. The activities are AA (event 1 to 2), BB (1 to 3), CC (2 to 5), DD (3 to 4), EE (5 to 6) and FF (4 to 6). There is also a dummy activity from event 2 to event 3 and another dummy from event 4 to event 5.
    (a)
    What are the immediate predecessors of activity DD?
    [1 mark]
    • ABB only
    • BAA and BB
    • CAA only
    • DAA, BB and CC
    (b)
    Which activity can start as soon as DD has finished, without waiting for any other activity to finish?
    [1 mark]
    • AEE
    • BEE and FF
    • CNeither, because of the dummy
    • DFF
    (c)
    Complete the precedence table by giving the immediate predecessors of each of the activities AA to FF.
    [2 marks]

    Total for question 1: 4 marks

  2. 2
    A project has seven activities. Each activity, its duration in days and its immediate predecessors are: AA 4 (none); BB 6 (none); CC 3 (AA); DD 5 (AA, BB); EE 7 (CC); FF 4 (DD); GG 5 (EE, FF).
    (a)
    What is the minimum time in which the project can be completed?
    [1 mark]
    • A2020 days
    • B1919 days
    • C3434 days
    • D1515 days
    (b)
    Which activities are on the critical path?
    [1 mark]
    • AAA, CC, EE, GG
    • BAA, DD, FF, GG
    • CBB, DD, FF, GG
    • DBB, DD, EE, GG
    (c)
    Find the total float of activity CC.
    [2 marks]

    Total for question 2: 4 marks

  3. 3
    A project has six activities. Each activity, its duration in days, the number of workers it needs and its immediate predecessors are: AA 2 days, 3 workers (none); BB 4 days, 2 workers (none); CC 3 days, 1 worker (none); DD 4 days, 1 worker (CC); EE 4 days, 3 workers (AA); FF 3 days, 2 workers (DD). The minimum completion time of the project is 10 days, and the critical activities are CC, DD and FF.
    (a)
    Every activity starts at its earliest possible time. Find the number of workers needed on each of the ten days.
    [3 marks]
    (b)
    Only 4 workers are available at any time. Show that the project can still be completed in 10 days by delaying one activity, and give the start time of every activity.
    [4 marks]

    Total for question 3: 7 marks

  4. 4
    A project has seven activities, each needing one worker. Each activity, its duration in days and its immediate predecessors are: AA 4 (none); BB 4 (none); CC 6 (AA); DD 6 (AA); EE 3 (BB, CC, DD); FF 5 (none); GG 2 (EE).
    (a)
    Carry out a forward pass and a backward pass to find the earliest and latest start times of every activity, the minimum completion time, the critical activities and the total float of BB and of FF.
    [6 marks]
    (b)
    Find a lower bound for the number of workers needed to complete the project in the minimum time, and construct a schedule, stating which activities each worker does and when, that achieves this.
    [6 marks]

    Total for question 4: 12 marks

  5. 5
    A project has four activities, KK, LL, MM and NN. Their immediate predecessors are: KK none; LL none; MM is preceded by KK and LL; NN is preceded by LL only. The project is to be modelled by an activity network with activities on arcs.
    (a)
    What is the least number of dummy activities needed in the network?
    [1 mark]
    • A00
    • B22
    • C11
    • D33
    (b)
    Which statement describes the dummy activity?
    [1 mark]
    • AIt runs from the end of LL to the start of MM, so that MM follows both KK and LL while NN follows only LL
    • BIt runs from the end of KK to the start of NN, so that NN follows KK
    • CIt runs from the end of MM to the start of NN, so that NN follows MM
    • DIt runs from the end of NN to the start of MM, so that MM follows NN
    (c)
    Two more activities are added: OO is preceded by MM and NN, and PP is preceded by NN only. State, with a reason, how many further dummy activities are needed.
    [2 marks]

    Total for question 5: 4 marks

  6. 6
    In a project each activity needs one worker. The sum of all the activity durations is 70 days and the minimum project time is 30 days. Activity XX lasts 6 days. Its start event has earliest event time 5 and its finish event has latest event time 17.
    (a)
    What is the total float of activity XX?
    [1 mark]
    • A1212 days
    • B1111 days
    • C2828 days
    • D66 days
    (b)
    Activity XX is delayed by 4 days. What is the effect on the minimum project time?
    [1 mark]
    • AIt increases by 4 days
    • BThere is no effect
    • CIt increases by 2 days
    • DIt increases by 6 days
    (c)
    Find a lower bound for the number of workers needed to complete the project in 30 days.
    [2 marks]

    Total for question 6: 4 marks

  7. 7
    A project has six activities. Each activity, its duration in days, the number of workers it needs and its immediate predecessors are: AA 5 days, 2 workers (none); BB 2 days, 1 worker (none); CC 5 days, 1 worker (none); DD 5 days, 1 worker (BB); EE 2 days, 3 workers (BB); FF 3 days, 2 workers (AA, DD, EE). The minimum completion time is 10 days and the critical activities are BB, DD and FF.
    (a)
    Every activity starts at its earliest possible time. Find the number of workers needed on each of the ten days.
    [3 marks]
    (b)
    Only 4 workers are available at any time. Show that the project can still be completed in 10 days by delaying one activity, and give the start time of every activity.
    [4 marks]

    Total for question 7: 7 marks

  8. 8
    A project has seven activities, each needing one worker. Each activity, its duration in days and its immediate predecessors are: AA 7 (none); BB 2 (none); CC 7 (BB); DD 5 (none); EE 2 (CC); FF 4 (AA, CC); GG 5 (EE).
    (a)
    Carry out a forward pass and a backward pass to find the minimum completion time, the critical activities and the total float of AA, DD and FF.
    [6 marks]
    (b)
    Find a lower bound for the number of workers needed to complete the project in the minimum time, and construct a schedule, stating which activities each worker does and when, that achieves this.
    [6 marks]

    Total for question 8: 12 marks

End of questions

Written by the Exaim team, led by Shaun Daswani (Head of Upper Secondary, Improve ME Institute; MSc Financial Mathematics, Imperial College London; BSc, UCL) and Jason Daswani (operational lead, Improve ME Institute; LSE).