Gantt charts, resource histograms and levelling Flashcards
Studying this course? Keep your progress in one place.

Flip each card. Be honest: the ones you mark Not yet come back first.
13 cards
Tap a card to flip it. Swipe right if you knew it, left if not.
See all 13 cards
- What does a cascade (Gantt) diagram show?
- Each activity as a horizontal bar against time, with its float, so you can see which activities run at any moment.
- In a cascade diagram, where do the bars of non-critical activities start?
- At their earliest start time, with the float drawn after the bar.
- Formula for the float of an activity?
- Latest finish earliest start duration.
- What is a resource histogram?
- A bar chart of the number of workers needed in each time period.
- How do you read the peak demand from a histogram?
- It is the tallest bar: the most workers needed at any one time.
- How do you find total worker-days?
- Sum of (duration workers) over all activities, which is the area under the histogram.
- What is resource levelling?
- Delaying non-critical activities within their floats to reduce peaks in demand without delaying the project.
- Why is levelling done with a heuristic?
- There is no method guaranteed to give the best schedule, so a sensible rule is used and checked.
- Which activities must you not delay when levelling?
- Critical activities, because delaying them delays the whole project.
- Lower bound for the number of workers (one worker per activity)?
- , rounded up.
- Total duration 27 days, minimum time 16 days. Lower bound?
- , so at least 2 workers.
- What must you do after finding the lower bound?
- Give a schedule showing that this number of workers is sufficient, respecting all precedences.
- What happens if a resource limit cannot be met without moving critical activities?
- The project completion time must increase.