Critical paths and floatEdexcel A-Level Further Maths: Mind map

Forward pass
Backward pass

Critical path analysis

times, float and workers

Forward passBackward passFloat
Critical path
Total float
Gantt and workers

Exam questions on Critical paths and float

  1. A project has eight activities. Each activity, its duration in days and its immediate predecessors are: A 4 (none); B 6 (none); C 5 (A); D 3 (A, B); E 7 (B); F 4 (C, D); G 2 (D, E); H 3 (F, G). The earliest start time of an activity is the earliest time at which all of its predecessors are complete.
    Find the total float of activity C.2 marks
  2. A project has seven activities. Each activity, its duration in days and its immediate predecessors are: A 3 (none); B 5 (none); C 4 (A); D 2 (A); E 6 (B, C); F 3 (D); G 4 (E, F). Each activity needs one worker.
    Find the total float of activity D.2 marks
  3. A project has seven activities. Each activity, its duration in days and its immediate predecessors are: A 5 (none); B 3 (none); C 4 (A); D 6 (A, B); E 2 (B); F 5 (C, D); G 4 (D, E). Activities start as soon as they can.
    Carry out a forward pass to find the earliest start time of each activity. State the minimum project completion time and the critical activities.3 marks