Critical paths and floatEdexcel A-Level Further Maths: Mind map
Forward pass
Backward pass
Critical path analysis
times, float and workers
Forward passBackward passFloat
Critical path
Total float
Gantt and workers
Exam questions on Critical paths and float
- A project has eight activities. Each activity, its duration in days and its immediate predecessors are: A 4 (none); B 6 (none); C 5 (A); D 3 (A, B); E 7 (B); F 4 (C, D); G 2 (D, E); H 3 (F, G). The earliest start time of an activity is the earliest time at which all of its predecessors are complete.Find the total float of activity C.2 marks
- A project has seven activities. Each activity, its duration in days and its immediate predecessors are: A 3 (none); B 5 (none); C 4 (A); D 2 (A); E 6 (B, C); F 3 (D); G 4 (E, F). Each activity needs one worker.Find the total float of activity D.2 marks
- A project has seven activities. Each activity, its duration in days and its immediate predecessors are: A 5 (none); B 3 (none); C 4 (A); D 6 (A, B); E 2 (B); F 5 (C, D); G 4 (D, E). Activities start as soon as they can.Carry out a forward pass to find the earliest start time of each activity. State the minimum project completion time and the critical activities.3 marks
Written by the Exaim team, led by Shaun Daswani (Head of Upper Secondary, Improve ME Institute; MSc Financial Mathematics, Imperial College London; BSc, UCL) and Jason Daswani (operational lead, Improve ME Institute; LSE).