All worksheets topics

Critical paths and floatEdexcel A-Level Further Maths: Subtopic test

10 questions, 27 marks

Edexcel A-Level Further Maths

Critical paths and float

Total 27 marks

Name

Class

Date

  1. 1
    A project has eight activities. Each activity, its duration in days and its immediate predecessors are: A 4 (none); B 6 (none); C 5 (A); D 3 (A, B); E 7 (B); F 4 (C, D); G 2 (D, E); H 3 (F, G). The earliest start time of an activity is the earliest time at which all of its predecessors are complete.
    (a)
    What is the earliest start time of activity G?
    [1 mark]
    • A9
    • B15
    • C13
    • D18
    (b)
    Which activities are critical?
    [1 mark]
    • AA, C, F, H
    • BB, E, G, H
    • CB, D, G, H
    • DA, D, F, H
    (c)
    Find the total float of activity C.
    [2 marks]

    Total for question 1: 4 marks

  2. 2
    A project has seven activities. Each activity, its duration in days and its immediate predecessors are: A 3 (none); B 5 (none); C 4 (A); D 2 (A); E 6 (B, C); F 3 (D); G 4 (E, F). Each activity needs one worker.
    (a)
    What is the minimum completion time of the project?
    [1 mark]
    • A13
    • B27
    • C15
    • D17
    (b)
    What is the lower bound for the number of workers needed to complete the project in the minimum time?
    [1 mark]
    • A2
    • B1
    • C3
    • D4
    (c)
    Find the total float of activity D.
    [2 marks]

    Total for question 2: 4 marks

  3. 3
    A project has seven activities. Each activity, its duration in days and its immediate predecessors are: A 5 (none); B 3 (none); C 4 (A); D 6 (A, B); E 2 (B); F 5 (C, D); G 4 (D, E). Activities start as soon as they can.
    (a)
    Carry out a forward pass to find the earliest start time of each activity. State the minimum project completion time and the critical activities.
    [3 marks]
    (b)
    Carry out a backward pass and hence find the total float of each non-critical activity.
    [4 marks]

    Total for question 3: 7 marks

  4. 4
    A project has nine activities. Each activity, its duration in days and its immediate predecessors are: A 6 (none); B 4 (none); C 5 (A); D 7 (A); E 3 (B); F 4 (B, C); G 6 (D, E); H 2 (F); I 5 (G, H). Each activity needs one worker.
    (a)
    Use a forward and backward pass to find the minimum project completion time and the critical activities. Hence find a lower bound for the number of workers needed to complete the project in this time.
    [6 marks]
    (b)
    Unexpectedly, activity C takes 8 days instead of 5. Decide, with working, whether the project is delayed, and find the new critical activities.
    [6 marks]

    Total for question 4: 12 marks

End of questions

Written by the Exaim team, led by Shaun Daswani (Head of Upper Secondary, Improve ME Institute; MSc Financial Mathematics, Imperial College London; BSc, UCL) and Jason Daswani (operational lead, Improve ME Institute; LSE).