Critical paths and floatEdexcel A-Level Further Maths: Subtopic test
10 questions, 27 marks
Edexcel A-Level Further Maths
Critical paths and float
Total 27 marks
Name
Class
Date
- 1A project has eight activities. Each activity, its duration in days and its immediate predecessors are: A 4 (none); B 6 (none); C 5 (A); D 3 (A, B); E 7 (B); F 4 (C, D); G 2 (D, E); H 3 (F, G). The earliest start time of an activity is the earliest time at which all of its predecessors are complete.(a)What is the earliest start time of activity G?[1 mark]
- A9
- B15
- C13
- D18
(b)Which activities are critical?[1 mark]- AA, C, F, H
- BB, E, G, H
- CB, D, G, H
- DA, D, F, H
(c)Find the total float of activity C.[2 marks]Total for question 1: 4 marks
- 2A project has seven activities. Each activity, its duration in days and its immediate predecessors are: A 3 (none); B 5 (none); C 4 (A); D 2 (A); E 6 (B, C); F 3 (D); G 4 (E, F). Each activity needs one worker.(a)What is the minimum completion time of the project?[1 mark]
- A13
- B27
- C15
- D17
(b)What is the lower bound for the number of workers needed to complete the project in the minimum time?[1 mark]- A2
- B1
- C3
- D4
(c)Find the total float of activity D.[2 marks]Total for question 2: 4 marks
- 3A project has seven activities. Each activity, its duration in days and its immediate predecessors are: A 5 (none); B 3 (none); C 4 (A); D 6 (A, B); E 2 (B); F 5 (C, D); G 4 (D, E). Activities start as soon as they can.(a)Carry out a forward pass to find the earliest start time of each activity. State the minimum project completion time and the critical activities.[3 marks](b)Carry out a backward pass and hence find the total float of each non-critical activity.[4 marks]
Total for question 3: 7 marks
- 4A project has nine activities. Each activity, its duration in days and its immediate predecessors are: A 6 (none); B 4 (none); C 5 (A); D 7 (A); E 3 (B); F 4 (B, C); G 6 (D, E); H 2 (F); I 5 (G, H). Each activity needs one worker.(a)Use a forward and backward pass to find the minimum project completion time and the critical activities. Hence find a lower bound for the number of workers needed to complete the project in this time.[6 marks](b)Unexpectedly, activity C takes 8 days instead of 5. Decide, with working, whether the project is delayed, and find the new critical activities.[6 marks]
Total for question 4: 12 marks
End of questions
Written by the Exaim team, led by Shaun Daswani (Head of Upper Secondary, Improve ME Institute; MSc Financial Mathematics, Imperial College London; BSc, UCL) and Jason Daswani (operational lead, Improve ME Institute; LSE).