Critical paths and float

Critical paths and float Flashcards

Spec 4.3–4 · Edexcel A-Level Further Maths: Flashcards

Studying this course? Keep your progress in one place.

Flip each card. Be honest: the ones you mark Not yet come back first.

12 cards

Tap a card to flip it. Swipe right if you knew it, left if not.

See all 12 cards
What does a forward pass find?
The earliest event times, taking the largest value at each event.
What does a backward pass find?
The latest event times, taking the smallest value at each event.
What is the minimum project time?
The earliest event time at the finish event.
Earliest finish of an activity?
Earliest start + duration.
Latest start of an activity?
Latest finish − duration.
What is a critical activity?
One with zero total float, so any delay delays the project.
What is the critical path?
The longest path from start to finish.
Formula for total float?
F(i, j) = l(j) − e(i) − duration(i, j).
An activity has float 2 and is delayed by 5 days. What is the effect?
The project is delayed by 3 days.
Can a network have more than one critical path?
Yes.
What is a Gantt (cascade) chart?
A chart of bars against time showing when each activity takes place, with one worker per activity.
Lower bound for the number of workers?
Sum of durations ÷ project time, rounded up.

Flashcards