Critical paths and float Flashcards
Studying this course? Keep your progress in one place.

Flip each card. Be honest: the ones you mark Not yet come back first.
12 cards
Tap a card to flip it. Swipe right if you knew it, left if not.
See all 12 cards
- What does a forward pass find?
- The earliest event times, taking the largest value at each event.
- What does a backward pass find?
- The latest event times, taking the smallest value at each event.
- What is the minimum project time?
- The earliest event time at the finish event.
- Earliest finish of an activity?
- Earliest start + duration.
- Latest start of an activity?
- Latest finish − duration.
- What is a critical activity?
- One with zero total float, so any delay delays the project.
- What is the critical path?
- The longest path from start to finish.
- Formula for total float?
- F(i, j) = l(j) − e(i) − duration(i, j).
- An activity has float 2 and is delayed by 5 days. What is the effect?
- The project is delayed by 3 days.
- Can a network have more than one critical path?
- Yes.
- What is a Gantt (cascade) chart?
- A chart of bars against time showing when each activity takes place, with one worker per activity.
- Lower bound for the number of workers?
- Sum of durations ÷ project time, rounded up.