Resource histograms and scheduling

Resource histograms and scheduling Flashcards

Spec 4.5–6 · Edexcel A-Level Further Maths: Flashcards

Studying this course? Keep your progress in one place.

Flip each card. Be honest: the ones you mark Not yet come back first.

12 cards

Tap a card to flip it. Swipe right if you knew it, left if not.

See all 12 cards
What is a resource histogram?
A chart of the number of workers needed against time.
What is a worker-day?
One worker working for one day; workers × days.
What does the area of a block represent?
The worker-days of that activity.
Which start times are used to build a basic histogram?
The earliest start times of the activities.
How do you find the number of workers in an interval?
Add the workers of all activities in progress then.
What is resource levelling?
Moving non-critical activities within their floats to reduce the peak number of workers.
Can critical activities be moved in levelling?
No, that would delay the project.
What happens if an activity is delayed by less than its float?
The project time does not change.
What is scheduling?
Allocating activities to workers and times so that all precedences are met.
Lower bound for the number of workers?
Sum of durations ÷ project time, rounded up.
Where do you put the critical activities in a schedule?
Give them to one worker, with no gaps.
What must you check in a schedule?
Each worker does one activity at a time and every precedence holds.

Flashcards