Gantt charts and scheduling

Gantt charts and scheduling Flashcards

Spec 4.4 · Edexcel International A Level Maths: Flashcards

Studying this course? Keep your progress in one place.

Flip each card. Be honest: the ones you mark Not yet come back first.

13 cards

Tap a card to flip it. Swipe right if you knew it, left if not.

See all 13 cards
What is a cascade (Gantt) chart?
A time-scaled chart with a bar for each activity showing its start, finish and float.
What are the ends of an activity's bar on a standard cascade chart?
Earliest start and earliest finish.
How is float shown on a cascade chart?
As a dotted line after the bar, up to the latest finish time.
How do you find which activities are in progress at time tt?
Draw a vertical line at time tt and read the bars it crosses.
How do you find the minimum completion time from the chart?
It is the finish time of the last critical activity.
How is a critical activity shown on a chart?
As a bar with no float line.
What delay does an activity cause if it is delayed by more than its float?
The project is delayed by the excess (delay minus float).
What is scheduling?
Allocating activities to workers and times so that precedence is respected.
What assumptions are made in scheduling?
Each worker does one activity at a time; activities are not interrupted or shared.
State the lower bound for the number of workers.
Total of the activity durations divided by the completion time, rounded up.
Total of durations is 27 and the project takes 16 days. Lower bound for workers?
2716=1.69\frac{27}{16}=1.69, so at least 2 workers.
Why may more workers than the lower bound be needed?
Precedence prevents even sharing of work, so workers are idle at times.
Who should do the critical activities in a schedule?
One worker, at their earliest times, because they have no float.

Flashcards